Dabbs House Road Improvements
Project Status: Completed
Estimated Cost: $13.3 million total
Start Date: 2020
Actual End Date: 2nd Quarter, 2024
Magisterial District: Varina
Henrico County will be improving an approximately 0.896 mile section of Dabbs House Road between Nine Mile Road and 0.075 miles north of the intersection of Dabbs House Road and Kingsridge Parkway. The project includes widening the road to a width of 40 feet, installing curb and gutter, drainage improvements, and sidewalk on one side of the road. A right turn lane will be added on Nine Mile Road at Dabbs House Road.
A future project is to connect Dabbs House Road with Kingsridge Parkway and to install a traffic signal at the intersection of Kingsridge Parkway and E. Laburnum Avenue.
Estimated Schedule
- Utility relocation is complete
- Advertisement is complete
- Construction is underway
- Project completed May 2024