N Parham Rd Sidewalk #3

Project Status: Underway - Construction

Estimated Cost: $1.3 million
Start Date: 2nd Quarter, 2026
Estimated End Date: 2027

Magisterial District:   Tuckahoe  


Description

This project consists of installing approximately 1,100 LF of concrete sidewalk along the western side of N. Parham Road from Holly Hill Road to Weldon Drive.  

Estimated Schedule

  • Design is complete
  • Right-of-way acquisition is complete
  • Utility relocation is complete
  • Construction to begin in 2nd Quarter, 2026

Progress to Date

  • A public information meeting for this project was held Wednesday, May 8th from 5:30- 7 pm at Ridge Elementary School, 8910 Three Chopt Rd. Henrico, VA 23229. Meeting documents can be found below.