N Parham Rd Sidewalk #3

Project Summary

Project Status
Underway - Construction
Estimated Cost
$1.3 million
Start Date
2nd Quarter, 2026
Estimated End Date
2027
Magisterial District
Tuckahoe

Project Description

Description

This project consists of installing approximately 1,100 LF of concrete sidewalk along the western side of N. Parham Road from Holly Hill Road to Weldon Drive.  

Estimated Schedule

  • Design is complete
  • Right-of-way acquisition is complete
  • Utility relocation is complete
  • Construction is underway

 

Amenities

  • Pedestrian SignalPedestrian Signal
  • SidewalkSidewalk

Progress to Date

  • A public information meeting for this project was held Wednesday, May 8th, 2024 from 5:30- 7 pm at Ridge Elementary School, 8910 Three Chopt Rd. Henrico, VA 23229. Meeting documents can be found below.

Project Resources