N Parham Rd Sidewalk #3
Project Summary
- Project Status
- Underway - Construction
- Estimated Cost
- $1.3 million
- Start Date
- 2nd Quarter, 2026
- Estimated End Date
- 2027
- Magisterial District
- Tuckahoe
Project Description
Description
This project consists of installing approximately 1,100 LF of concrete sidewalk along the western side of N. Parham Road from Holly Hill Road to Weldon Drive.
Estimated Schedule
- Design is complete
- Right-of-way acquisition is complete
- Utility relocation is complete
- Construction is underway
Amenities
Pedestrian Signal
Sidewalk
Progress to Date
- A public information meeting for this project was held Wednesday, May 8th, 2024 from 5:30- 7 pm at Ridge Elementary School, 8910 Three Chopt Rd. Henrico, VA 23229. Meeting documents can be found below.