Nuckols Road Turn Lane (I-295 to Lake Brook Drive)

Project Status: Completed

Start Date: October 9, 2017
Estimated End Date: December 31, 2017

Magisterial District:   Three Chopt  


This project consists of the construction of an additional westbound lane from Lakebrook Drive to the on-ramp for I-295.  The total length of the 11-foot wide road widening is approximately 560 linear feet. 

There will also be work at the intersection of Lake Brook Drive and Nuckols Road to adjust/replace the curb and gutter in the radius as well as the ADA ramp, traffic signal pole, and fire hydrant.

Construction Hours:

  • Daily between 9:00 a.m. – 3:30 p.m.
  • Paving and striping work between 9:00 p.m. – 6:00 a.m. (may occur)

Progress to Date

  • Construction to begin October 9, 2017.
  • Estimated project completion: December 31, 2017