Staples Mill Pedestrian Improvements
Project Status: Underway - Right of Way Acquisition
Estimated Cost: $4.5 million
Start Date: 2027
Estimated End Date: 2028
Magisterial District: Brookland
The Project provides for safe pedestrian access at nine (9) intersections along Staples Mill Road between Aspen Avenue and Janway Road. Improvements include the installation of sidewalk, curb ramps, crosswalks, pedestrian push buttons, and intersection lighting.
The nine (9) intersections are –
- Staples Mill Road and Aspen Avenue/Townhouse Road
- Staples Mill Road and Penick Road
- Staples Mill Road and Hilliard Road/Glenside Drive
- Staples Mill Road and Crockett Street
- Staples Mill Road and Bremner Boulevard
- Staples Mill Road and Wistar Road
- Staples Mill Road and Hermitage Road
- Staples Mill Road and Stoneman Road
- Staples Mill Road and Janway Road
Estimated Schedule:
- Design is underway.
- Right-of-Way acquisition is underway.
- Utility relocation is not anticipated.
- Advertisement for construction is anticipated for 2027.
- Construction to begin in 2027.