Staples Mill Pedestrian Improvements
Project Status: Underway - Design
Estimated Cost: $4.5m
Start Date: 2027
Estimated End Date: 2027
Magisterial District: Brookland
The Project provides for safe pedestrian access at nine (9) intersections along Staples Mill Road between Aspen Avenue and Janway Road.
The nine (9) intersections are –
- Staples Mill Road and Aspen Avenue/Townhouse Road
- Staples Mill Road and Penick Road
- Staples Mill Road and Hilliard Road/Glenside Drive
- Staples Mill Road and Crockett Street
- Staples Mill Road and Bremner Boulevard
- Staples Mill Road and Wistar Road
- Staples Mill Road and Hermitage Road
- Staples Mill Road and Stoneman Road
- Staples Mill Road and Janway Road
Progress to Date
- Design underway.
- Right-of-Way acquisition is anticipated to begin in 2nd Quarter, 2025.
- Utility relocation is anticipated to begin in 4th Quarter, 2025.
- Advertisement for construction is anticipated for 2026.
- Construction to begin in 2027.