Staples Mill Pedestrian Improvements

Project Status: Underway - Design

Estimated Cost: $4.5m
Start Date: 2027
Estimated End Date: 2027

Magisterial District:   Brookland  


The Project provides for safe pedestrian access at nine (9) intersections along Staples Mill Road between Aspen Avenue and Janway Road.

The nine (9) intersections are –  

  1. Staples Mill Road and Aspen Avenue/Townhouse Road
  2. Staples Mill Road and Penick Road
  3. Staples Mill Road and Hilliard Road/Glenside Drive
  4. Staples Mill Road and Crockett Street
  5. Staples Mill Road and Bremner Boulevard
  6. Staples Mill Road and Wistar Road
  7. Staples Mill Road and Hermitage Road
  8. Staples Mill Road and Stoneman Road
  9. Staples Mill Road and Janway Road

Progress to Date

  • Design underway.
  • Right-of-Way acquisition is anticipated to begin in 2nd Quarter, 2025.
  • Utility relocation is anticipated to begin in 4th Quarter, 2025.
  • Advertisement for construction is anticipated for 2026.
  • Construction to begin in 2027.