Project Status
Underway - Design
Estimated Cost
$12.2M
Start Date
2028
Estimated End Date
2030
Magisterial District
Brookland   Tuckahoe

Project Description

The County of Henrico will be constructing accommodations to improve pedestrian and vehicular infrastructure as well as safety and accessibility at the intersection. The following improvements will be constructed:

  • Third through lane on Glenside Drive southbound.
  • Widening of Glenside Drive northbound to accommodate a second dedicated left-turn and second dedicated through lane.  Sidewalk along the west side of Glenside Drive.
  • Pedestrian crossings with curb ramps, marked crossings, and pedestrian signals on the west and north legs of the intersection.
  • Bus shelter on the east side of W. Broad Street just north of Glenside Drive. 

Estimated Schedule: (Quarter Year)

  • Design is underway
  • Right-of-way acquisition is anticipated to begin 2027
  • Utility relocation is anticipated to begin 2028
  • Advertisement for construction is anticipated to begin 2028
  • Construction is anticipated to begin 2028