Woodman Road Improvements
Project Summary
- Project Status
- Underway - Design
- Estimated Cost
- $80 million
- Start Date
- 2030
- Estimated End Date
- 2032
Project Description
The County of Henrico is proposing to improve 1.75 miles of Woodman Road to provide a four-lane divided roadway between Hungary Road and Mountain Road. The project includes turn lane improvements, a shared use path, and sidewalk along the corridor. Pedestrian crossings with push buttons and count down timers will be provided at each signalized intersection.
Estimated Schedule
- Design is underway.
- Right-of-way acquisition is anticipated to begin in 2027.
- Utility relocation is anticipated to begin in 2028.
- Advertisement for construction is anticipated for 2030.
- Construction is anticipated to begin in 2030.
Amenities
Pedestrian Signal
Road Widening
Shared-Use Path
Sidewalk
Progress to Date
-
- A public hearing was held July 24, 2025 from 5:30 pm to 7:00 pm at Brookland Middle School, 9200 Lydell Drive, Henrico, VA 23228. Meeting documents from this meeting can be found below.
- A public information meeting was held on Monday, May 13, 2024 from 5:30 pm to 7:00 pm at Brookland Middle School, 9200 Lydell Drive, Henrico, VA 23228.