Woodman Road Improvements

Project Summary

Project Status
Underway - Design
Estimated Cost
$80 million
Start Date
2030
Estimated End Date
2032
Magisterial District
Brookland   Fairfield

Project Description

The County of Henrico is proposing to improve 1.75 miles of Woodman Road to provide a four-lane divided roadway between Hungary Road and Mountain Road. The project includes turn lane improvements, a shared use path, and sidewalk along the corridor. Pedestrian crossings with push buttons and count down timers will be provided at each signalized intersection.

Estimated Schedule

  • Design is underway.
  • Right-of-way acquisition is anticipated to begin in 2027.
  • Utility relocation is anticipated to begin in 2028.
  • Advertisement for construction is anticipated for 2030.
  • Construction is anticipated to begin in 2030.

Amenities

  • Pedestrian SignalPedestrian Signal
  • Road WideningRoad Widening
  • Shared-Use PathShared-Use Path
  • SidewalkSidewalk

Progress to Date

    • A public hearing was held July 24, 2025 from 5:30 pm to 7:00 pm at Brookland Middle School, 9200 Lydell Drive, Henrico, VA 23228. Meeting documents from this meeting can be found below.
    • A public information meeting was held on Monday, May 13, 2024 from 5:30 pm to 7:00 pm at Brookland Middle School, 9200 Lydell Drive, Henrico, VA 23228. 

 