Ridge Road Sidewalk, Phase 1
Project Status: Completed
Estimated Cost: $740,000
Start Date: 1st Quarter, 2024
Estimated End Date: Complete - June 2024
Magisterial District: Tuckahoe
The County of Henrico will be constructing approximately 1,920 feet of 5-foot-wide sidewalk with a 2-foot-wide grass strip along the southwest side of Ridge Road between Old Providence Circle and North Ridge Road. In addition, approximately 260 feet of new curb and gutter will be constructed between Ziontown Road and the adjacent business parcel.
Estimated Schedule
- Design is complete.
- Right-of-way acquisition is complete.
- Utility relocations are complete.
- Advertisement for construction is completed.
- Construction was completed June 2024.
Progress to Date
- A Public Hearing to discuss project details will be held on Wednesday, June 9, 2021 at the Tuckahoe Library from 5:30 PM to 6:30 PM.