Church Road Safety and Mobility Improvements

Project Status: Completed

Estimated Cost: $1.5 million
Start Date: August 2021
Estimated End Date: September 2021

Magisterial District:   Three Chopt   Tuckahoe  


Henrico County  is evaluated Church Road from John Rolfe Parkway to west of Lauderdale Drive.   Public input was sought on reconfiguring the existing 4 lane undivided roadway to improve safety and mobility for all users. 

A virtual public information meeting and online comment period was available from November 13 through November 25, 2020We received 426 responses via online survey and email. The responses provided feedback on the safety needs for the corridor, as well as three conceptual options for consideration.  The user feedback showed that 76% of respondents felt the current roadway did not adequately address safety concerns. Crosswalks were desired by 71% of respondents and 58% would like the addition of bicycle lanes. The dual bike lanes with median conceptual option was supported by 71% of the respondents. Below is a link to the public feedback summary: 

Church Road Safety and Mobility Study Findings – Summary

The preferred concept design was refined and constructed. Below are before and after photos.

Before:

 

 

 

 

 

 

 

After:

Contact Us

Sharon Smidler
(804) 501-4621
[email protected]


Public Works

Henrico Department of Public Works
4305 E. Parham Rd.
Henrico, VA 23228

Phone
(804) 501-4393

[email protected]

Mailing Address
P. O. Box 90775
Henrico, VA 23273-0775

Twitter Facebook

 
Google Translate Icon

Translate