Gay Avenue Sidewalk Improvements
Project Status: Completed
Estimated Cost: $3,089,031
Start Date: September 2021
Estimated End Date: July 2022
Magisterial District: Varina
The County of Henrico will be constructing the following improvements:
|
Estimated Schedule
- Design began February 2017.
- Right-of-way acquisition completed April 2021.
- Utility relocation completed April 2021.
- Advertised for Construction May 2021.
- Construction started September 2021.
- Project completion is anticipated July 2022.
Progress to Date
- A citizen information meeting was held August 2017.