E. Laburnum Avenue Sidewalk Improvements
Project Status: Completed
Estimated Cost: $1,213,896
Start Date: June 2022
Estimated End Date: November 2022
Magisterial District: Fairfield
The County of Henrico will be constructing sidewalk along E. Laburnum Avenue. The following improvements will be constructed, including:
|
Estimated Schedule
- Design began in May 2018.
- Right-of-way acquisition was completed March 2021.
- Utility relocation was completed July 2021.
- Advertisement for construction was September 2021.
- Construction is anticipated to begin June 2022.
- Project completion is anticipated for November 2022.
Progress to Date
- Posted notice of willingness to hold a public hearing on July 2019. No comments were received.