Lake Overton Wet Pond Retrofit and Dam Safety Improvements

Henrico County Archives

This page content is archived for historical purposes.

Project Status: Underway - Construction

Estimated Cost: $2,295,286.98
Start Date: May 2024
Estimated End Date: February 2025

Magisterial District:   Fairfield  


The County of Henrico will retrofit the Lake Overton facility to a wet pond facility that will provide water quality improvements for the community. Included in this retrofit are dam safety improvements to the embankment. Future improvements include a trail connection to the Three Lakes Park trail system.  The following improvements will be constructed, including:

  • A sediment forebay
  • Shoreline erosion protection
  • Aquatic benches
  • Aeration fountain
  • Wooden retaining wall
  • New principal and auxiliary spillway
  • Dam embankment repairs
  • Forest mitigation plantings

Estimated Schedule: (Month Year)

  • Design is completed.
  • Right-of-way acquisition is completed.
  • Advertisement for construction is completed.
  • Utility coordination is anticipated to be completed in early May 2024
  • Construction is anticipated to begin May 2024

Progress to Date

  • Tree felling occurred between March 18th and March 29th.