Meadow Road Crossing

Project Status: In Progress

Estimated Cost: $1.9 million
Start Date: 4th Quarter, 2024
Estimated End Date: 2025

Magisterial District:   Varina  


The County of Henrico will be replacing the existing Meadow Road box culvert crossing over Boar Swamp Creek located between Crib Lane and Woodview Drive, with a new triple box culvert. The following improvements will be constructed, including: 

  • Removal of the existing structure. 
  • Construction of a triple box culvert on existing alignment. 
  • Installation of Guardrail System Improvements.

 

Estimated Schedule: (Month Year) 

  • Design began in January 2019. 
  • Right-of-way acquisition completed.  
  • Utility relocation is completed. 
  • Advertisement for construction is anticipated: 2nd Quarter, 2024 
  • Construction is anticipated to begin in 4th Quarter, 2024 
  • Project completion is anticipated in 2025 

Contact Us

Robert Whitaker III
(804) 727-8253
[email protected]


Public Works

Henrico Department of Public Works
4305 E. Parham Rd.
Henrico, VA 23228

Phone
(804) 501-4393

[email protected]

Mailing Address
P. O. Box 90775
Henrico, VA 23273-0775

Twitter Facebook

 
Google Translate Icon

Translate