Nuckols Rd Pedestrian Improvements

Project Status: Underway - Design

Estimated Cost: $1.7 million
Start Date: 1st Quarter, 2027
Estimated End Date: 2027

Magisterial District:   Brookland  


Design and construct sidewalk on the north side of Nuckols Road between Springfield Rd and Energy Way (formerly Capital One Way). Work will include crosswalks and pedestrian signals at the Nuckols Road and Energy Way intersection. 

Estimated Schedule: (Month Year) 

  • Design is underway
  • Right-of-way acquisition is anticipated to begin in 3rd Quarter, 2025
  • Utility relocation is anticipated to begin in 1st Quarter, 2026
  • Advertisement for construction is anticipated in 2026
  • Construction is anticipated to begin in 1st Quarter, 2027

Progress to Date

A Public Hearing was held on Monday, April 28, 2025 from 5:30 PM to 7:00 PM at the Glen Allen Library, 10501 Staples Mill Road, Glen Allen, VA 23060. Meeting documents can be found below.