Parham Road Pedestrian and Transit Stop Improvements
Project Status: Underway - Right of Way Acquisition
Estimated Cost: 998,000
Start Date: 2nd Quarter, 2024
Estimated End Date: 3rd Quarter, 2024
Magisterial District: Brookland
The County of Henrico will be constructing approximately 620 linear feet of 5-foot wide sidewalk, 430 linear feet of new curb & gutter and storm sewer along the 0.45-mile project corridor between Shrader Road and Hungary Spring Road. The following improvements will be constructed, including:
|
Estimated Schedule:
- Design is underway.
- Right-of-way acquisition is complete.
- Advertisement for construction is complete.
- Construction is anticipated to begin 2nd Quarter, 2024.
- Project completion is anticipated 3rd Quarter, 2024.
Progress to Date
- Pre-construction meeting held April 11, 2024
- Construction start date April 29, 2024