Parham Rd Pedestrian Intersection Improvements – Staples Mill Rd

Project Summary

Project Status
Underway - Right of Way Acquisition
Estimated Cost
$1.5 million
Start Date
2027
Estimated End Date
2027
Magisterial District
Brookland

Project Description

The Project provides for safe pedestrian access at Parham Road and Staples Mill Road intersection. The project also includes addition of approximately 200 feet of sidewalk improvements on Parham Road, east of Staples Mill Road.

Estimated Schedule

  • Design is complete.
  • Right of way acquisition is underway.
  • Utility relocation is complete.
  • Advertisement for construction is anticipated in 2027.
  • Construction is anticipated to begin in 2027.

Amenities

  • Pedestrian SignalPedestrian Signal
  • SidewalkSidewalk