Pump Road Sidewalk Project

Project Status: Completed

Estimated Cost: $1.9 million
Start Date: July 2021
Estimated End Date: April 2022

Magisterial District:   Three Chopt  


The County of Henrico will be constructing pedestrian access along the east side of Pump Road from Hazel Tree Drive to Kingsbury Court.  The following improvements will be constructed, including: 0.44 miles of 5-foot sidewalk, 2-foot wide utility strip, road widening, curb and gutter and storm sewer on the east side of Pump Road from Kingsbury Court to Hazel Tree Drive

Estimated Schedule

  • Design began May 2018.
  • Right-of-way acquisition was completed May 2020.
  • Utility relocation was completed February 2021.
  • Advertised for Construction January 2021.
  • Construction began July 2021.
  • Project completed April 2022.

Progress to Date

  • A Citizen Information Meeting was held on Monday, February 2019

Contact Us

Kevin Newcomb
(804) 501-5532
[email protected]


Public Works

Henrico Department of Public Works
4305 E. Parham Rd.
Henrico, VA 23228

Phone
(804) 501-4393

[email protected]

Mailing Address
P. O. Box 90775
Henrico, VA 23273-0775

Twitter Facebook

 
Google Translate Icon

Translate