Site menu

S. Laburnum Ave. Northbound Sidewalk

Project Status: Underway - Right of Way Acquisition

Estimated Cost: $2.8 Million
Start Date: 3rd Quarter, 2026
Estimated End Date: 2027

Magisterial District:   Varina  


Approximately 2,500 linear feet of new sidewalk along the eastern side of S. Laburnum Avenue from Audubon Drive to Williamsburg Road. Project includes upgrades to existing transit stops within the project limits.  

Estimated Schedule: (Month Year) 

  • Design is underway. 
  • Right-of-way acquisition is underway. 
  • Utility relocation is anticipated to start 2nd Quarter, 2026. 
  • Advertisement for construction is anticipated 3rd Quarter, 2026. 
  • Construction is anticipated to begin 3rd Quarter, 2026.