S. Laburnum Ave. Northbound Sidewalk

Project Status: Underway - Design

Estimated Cost: $1.9 Million
Start Date: 2026
Estimated End Date: 2027

Magisterial District:   Varina  


Approximately 2,500 linear feet of new sidewalk along the eastern side of S. Laburnum Avenue from Audobon Drive to Williamsburg Road. Project includes upgrades to existing transit stops within the project limits.  

Estimated Schedule: (Month Year) 

  • Design is underway. 
  • Right-of-way acquisition is anticipated to start 1st Quarter, 2025. 
  • Utility relocation is anticipated to start 4th Quarter, 2025. 
  • Advertisement for construction is anticipated 2026. 
  • Construction is anticipated to begin 2026.