Creighton Road – Phase II
Project Status: Underway - Construction
Estimated Cost: $17.89 million
Start Date: 1st Quarter, 2023
Estimated End Date: 2025
Magisterial District: Fairfield Varina
The County of Henrico will be constructing the following improvements:
|
Estimated Schedule
- Design is complete.
- Right-of-way acquisition is complete.
- Utility relocation is complete.
- Advertisement for construction is complete.
- Construction is underway.
- Project completion is anticipated in 2025.
Progress to Date
- A public hearing was held September 2014.
- The Creighton Road Bridge is complete as of March 3, 2017, and open for traffic.