Enterprise Parkway/Broad Street Area Sanitary Sewer Rehabilitation
Project Status: Completed
Start Date: January 2019
Estimated End Date: February 2020
Magisterial District: Brookland Tuckahoe
- The Enterprise Parkway and Broad Street Area Sanitary Sewer Rehabilitation project area is approximately bounded by Westland Shopping Center (north), West Broad Street (east), Wistar Street (south), and Biscayne Road/Prestwick Road (west).
- The Enterprise Parkway and Broad Street Area Sanitary Sewer Rehabilitation project will:
- Rehabilitate approximately 2,400 linear feet of sanitary sewer pipe
- Replace approximately 5,100 linear feet of sanitary sewer pipe
- A 108 linear feet jack and bore operation under West Broad Street