Maude Trevvett Elementary Connection

Project Status: Underway - Design

Estimated Cost: $850,000
Start Date: 2nd Quarter, 2025
Estimated End Date: 2026

Magisterial District:   Brookland   Fairfield  


The County of Henrico will be constructing the following improvements: 

  • Install approximately 450-ft of sidewalk and ADA ramps from Maude Trevvett Elementary School (Trevvett Drive) to Carter’s Bridge Place (east side of Woodman Road just south of E Parham Road). 

Estimated Schedule: 

  • Design began September 2022.
  • Right-of-way acquisition is complete.
  • Utility relocation is not required on this project. 
  • Advertisement for construction is anticipated 2nd Quarter, 2025.
  • Construction is anticipated to begin 2nd Quarter, 2025.

 

 

 