Mt. Olive Ave and Trolley Lane Improvements​

Project Status: Underway - Design

Estimated Cost: $5.1 million
Start Date: 4th Quarter, 2026
Estimated End Date: 2027

Magisterial District:   Fairfield  


The County of Henrico will be constructing accommodations to increase pedestrian access and connectivity. The following improvements will be constructed, including:

  • The removal of the existing connection of Mt. Olive Ave. to Mountain Road and constructing a new connection which reduces the existing skewed orientation.​
  • A right turn lane from Mountain Road to the new connection with Mt. Olive Ave. will be constructed.
  • Upgrading the existing gravel road which parallels the Dominion Energy transmission line easement.
  • The removal of the existing connection of Trolley Lane and Mountain Road.

Estimated Schedule: (Month Year)

  • Design ​​is underway.
  • Right-of-way acquisition is underway.
  • Utility relocation is anticipated to begin in the 2nd Quarter, 2026. 
  • Advertisement for construction is anticipated for ​3rd Quarter, 2026​.
  • Construction is anticipated to begin 4th Quarter, ​2026.