​​Nine Mile Rd Roadway Reconfiguration and Ped Safety ​

Project Status: Preliminary

Estimated Cost: ​​$8.9 M​
Start Date: 2028
Estimated End Date: 2029

Magisterial District:   Varina  


The County of Henrico will be constructing accommodations to increase pedestrian access and connectivity. The following improvements will be constructed, including: 

  • This project features roadway reconfiguration with other pedestrian crossings and connectivity enhancements along a segment of Nine Mile Road between Newbridge Road and Lee Avenue. 

Estimated Schedule: (Month Year) 

  • Design is anticipated to begin 1st Quarter, 2025 
  • Right-of-way acquisition is anticipated to begin 2027  
  • Utility relocation is anticipated to begin 2027 
  • Advertisement for construction is anticipated to begin 2028 
  • Construction is anticipated to begin 2028