Nuckols Road and Pouncey Tract Road Sidewalk

Project Status: Completed

Estimated Cost: $ 800,000 total
Start Date: March 16, 2020
Estimated End Date: August 2020

Magisterial District:   Three Chopt  


Henrico County is constructing approximately 1.4 miles of sidewalk that will run along the south side of Nuckols Road from Heatherford Drive to the intersection with Pouncey Tract Road and then along the west side of Pouncey Tract Road to Old Wyndham Drive.  Crosswalk and pedestrian signals will be installed as part of the project.

  • Design is completed
  • Right-of-way acquisition is complete
  • Construction began March 16, 2020
  • Project completion anticipated for August 2020

Progress to Date

  • A Citizen Information Meeting was held on Monday, April 24, 2017 from 6:00 PM to 7:30  PM.  The brochure provided at the meeting is now available.  

Contact Us

Paul Smith
(804) 501-5092
[email protected]


Public Works

Henrico Department of Public Works
4305 E. Parham Rd.
Henrico, VA 23228

Phone
(804) 501-4393

[email protected]

Mailing Address
P. O. Box 90775
Henrico, VA 23273-0775

Twitter Facebook

 
Google Translate Icon

Translate