​​W. Broad St. Pedestrian and Transit Improvements – Parham Road to Pemberton Road​

Project Status: Underway - Design

Estimated Cost: ​​$30 million​
Start Date: 2029
Estimated End Date: 2030

Magisterial District:   Brookland   Three Chopt  


The County of Henrico will be constructing improvements to multi-modal function, transit access, and pedestrian safety and accessibility along W. Broad Street between Parham Road and Pemberton Road. The following improvements will be constructed, including: 

  • Sidewalk facilities, where currently not installed, on both sides of Broad Street 
  • Curb ramps and crosswalks, proposed GRTC transit stops, and intersection modifications 

Estimated Schedule: (Month Year) 

  • Design is underway 
  • Right-of-way acquisition is anticipated to begin 1st Quarter, 2026 
  • Utility relocation is anticipated to begin 1st Quarter, 2028  
  • Advertisement for construction is anticipated 1st Quarter, 2029  
  • Construction is anticipated to begin 2nd Quarter 2029 

 

 

Progress to Date

Public Information meeting – The design public hearing was held on Wednesday, Dec. 13, 2023, 5-7 p.m., at R.C. Longan Elementary School located at 9200 Mapleview Ave., Henrico, VA 23294 


 