County-Wide Roundabouts

Project Status: Completed

Estimated Cost: $1,000,000
Start Date: May 2023
Actual End Date: September 2023

Magisterial District:   Brookland   Fairfield   Three Chopt   Tuckahoe   Varina  


The County of Henrico will be designing and constructing the following improvements: 

  • Several traffic calming projects throughout Henrico County, such as converting several temporary neighborhood roundabouts into permanent roadway features.  
  • Existing temporary roundabouts in the Charles Glen neighborhood (Brookland district), an existing temporary roundabout at Doron Lane & Oak Hill Lane (Fairfield District), and an existing temporary roundabout on Colleen Road and Subrenda Lane (Fairfield) will be constructed as permanent roadway features.  

Estimated Schedule: (Month Year) 

  • Design is underway. 
  • Right-of-way acquisition is not anticipated.  
  • Utility relocation is not anticipated. 
  • Advertisement for construction is anticipated to begin February 2023. 
  • Construction is anticipated to begin May 2023.  

Progress to Date

  • Construction is completed for the roundabout at Oak Hill Lane and Doron Lane.

  • Construction is anticipated for the roundabouts in Charles Glen in mid-June, 2023.  

  • Construction is anticipated for the roundabout on Colleen Road and Subrenda Lane in early fall 2023.  



 

Oak Hill Lane and Doron Lane

 

 


Contact Us

Ryan Levering
(804) 278-7505
[email protected]


Public Works

Henrico Department of Public Works
4305 E. Parham Rd.
Henrico, VA 23228

Phone
(804) 501-4393

[email protected]

Mailing Address
P. O. Box 90775
Henrico, VA 23273-0775

Twitter Facebook

 
Google Translate Icon

Translate