Project Summary
- Project Status
- Completed
- Estimated Cost
- $300,000
- Start Date
- 1st Quarter, 2026
- Estimated End Date
- 2nd Quarter, 2026
- Magisterial District
- Varina
Project Description
The County of Henrico will be constructing accommodations to increase pedestrian safety. The following improvements will be constructed, including:
- The installation of self-sustaining light fixtures to light the Virginia Capital Trail from the Richmond City limits south for approximately 1,100-ft to Old Delaware Street.
Estimated Schedule:
- Design is complete.
- Right-of-way acquisition is not anticipated.
- Utility relocation is not anticipated.
- Advertisement is complete.
- Construction is complete.