Darbytown Road & Doran Road Roundabout

Project Status: Underway - Design

Estimated Cost: $14.53 million
Start Date: 2027
Estimated End Date: 2028

Magisterial District:   Varina  


The County of Henrico will be constructing accommodations to increase pedestrian access and connectivity. The following improvements will be constructed, including: 

  • Realign Doran Road to tie into Darbytown across from Henry Ward Blvd. 
  • Construct a roundabout at the new Doran Road / Darbytown Road / Henry Ward Blvd intersection. 
  • Construct sidewalk along Doran and Darbytown Road.

Estimated Schedule: (Month Year) 

  • Design is underway.
  • Right-of-way acquisition is anticipated to begin 1st Quarter, 2026.  
  • Utility relocation is anticipated to begin 4th Quarter, 2026. 
  • Advertisement for construction is scheduled for 2027. 
  • Construction is anticipated to begin 2027. 

Progress to Date

There was a Public Information Meeting for the Darbytown Road & Doran Road Roundabout project on November 18, 2025 from 5:30pm – 7:00pm at Dorey Park – Henricus Room 2999 Darbytown Road Henrico, VA 23231

A comment response survey was able to be accessed until December 18th, 2025.