Site menu

Darbytown Road & Doran Road Roundabout

Project Summary

Project Status
Underway - Design
Estimated Cost
$14.8 million
Start Date
2028
Estimated End Date
2029
Magisterial District
Varina

Project Description

The County of Henrico will be constructing accommodations to increase pedestrian access and connectivity. The following improvements will be constructed, including: 

  • Realign Doran Road to tie into Darbytown across from Henry Ward Blvd. 
  • Construct a roundabout at the new Doran Road / Darbytown Road / Henry Ward Blvd intersection.
  • Construct sidewalks along Doran and Darbytown Road.

Estimated Schedule

  • Design is underway.
  • Right-of-way acquisition is anticipated to begin 3rd Quarter, 2026.  
  • Utility relocation is anticipated to begin in 2027. 
  • Advertisement for construction is anticipated to begin in 2027.
  • Construction is anticipated to begin 2028. 

Progress to Date

There was a Public Information Meeting for the Darbytown Road & Doran Road Roundabout project on November 18, 2025 from 5:30pm – 7:00pm at Dorey Park – Henricus Room 2999 Darbytown Road Henrico, VA 23231

A comment response survey was able to be accessed until December 18th, 2025.

 


Project Resources