Fall Line Trail – Brook and Hilliard Road Phase

Project Summary

Project Status
Advertised for Construction
Estimated Cost
$6.8 million
Start Date
4th Quarter, 2026
Estimated End Date
2028
Magisterial District
Fairfield

Project Description

The County of Henrico will be constructing approximately 2,800 linear feet of a minimum 12’ wide multi-use trail along with ADA compliant ramps along the north side of Hilliard Road and the west side of Brook Road from the northern end of the Lakeside Community Trail, Phase 3 to the intersection of Lakeside Avenue and Brook Road. This work will be a part of The Fall Line Trail, a 43-mile north-south paved trail that will connect Ashland to Petersburg.

 

Estimated Schedule

  • Design is complete. 
  • Right-of-way acquisition is complete.  
  • Utility relocations are complete.
  • Advertised for construction 6/30/26 as Fall Line Trail Southern Sections. Closes 8/13/26.
  • Construction is anticipated to begin in the 4th Quarter, 2026. 

Progress to Date

  • On Tuesday, May 16, 2023, the Henrico County Department of Public Works held a public information meeting from 5:00pm to 6:30pm at Lewis Ginter Botanical Gardens.  Materials from the meeting can be found in the Documents section below.  