Fall Line Trail – Brook and Hilliard Road Phase
Project Summary
- Project Status
- Advertised for Construction
- Estimated Cost
- $6.8 million
- Start Date
- 4th Quarter, 2026
- Estimated End Date
- 2028
- Magisterial District
- Fairfield
Project Description
The County of Henrico will be constructing approximately 2,800 linear feet of a minimum 12’ wide multi-use trail along with ADA compliant ramps along the north side of Hilliard Road and the west side of Brook Road from the northern end of the Lakeside Community Trail, Phase 3 to the intersection of Lakeside Avenue and Brook Road. This work will be a part of The Fall Line Trail, a 43-mile north-south paved trail that will connect Ashland to Petersburg.
Estimated Schedule
- Design is complete.
- Right-of-way acquisition is complete.
- Utility relocations are complete.
- Advertised for construction 6/30/26 as Fall Line Trail Southern Sections. Closes 8/13/26.
- Construction is anticipated to begin in the 4th Quarter, 2026.
Progress to Date
- On Tuesday, May 16, 2023, the Henrico County Department of Public Works held a public information meeting from 5:00pm to 6:30pm at Lewis Ginter Botanical Gardens. Materials from the meeting can be found in the Documents section below.