John Rolfe Parkway Sidewalk
Project Status: Completed
Estimated Cost: $679,000 total
Start Date: October 2018
Estimated End Date: Spring 2019
Magisterial District: Tuckahoe
Henrico County is constructing approximately 0.70 mile of sidewalk on John Rolfe Parkway between Ridgefield Parkway and Gayton Road. The design will evaluate placement of a 5’ wide sidewalk or another acceptable alternative. Crosswalk and pedestrian signals will be installed as part of the project.
Estimated Schedule
- Design is complete
- Right-of-way acquisition is complete
- Utility relocation is complete
- Project is underway as of October 4, 2018
- Project completion is anticipated in Spring 2019
Progress to Date
- A Citizen Information Meeting for this project was held on October 14th, 2015.