Messer Road Trail
Project Summary
- Project Status
- Underway - Design
- Estimated Cost
- $2.3 million
- Start Date
- 2032
- Estimated End Date
- 2033
- Magisterial District
- Varina
Project Description
The Messer Road Trail Connector is a proposed 12-foot-wide asphalt Shared Use Path along Messer Road to connect Varina High School to the Virginia Capital Trail at New Market Road (Route 5). The approximate length is 0.5-miles. The proposed alignment begins at the intersection of New Market Road and Messer Road and follows along the southeast side of Messer Road until terminating at the existing sidewalk in front of Varina High School.
Estimated Schedule
- Design is underway.
- Right-of-Way is anticipated in 2028.
- Utility relocation anticipated to begin 2030.
- Advertisement is anticipated to begin in 2031.
- Construction is anticipated to begin in 2032.
Progress to Date
- Public Information Meeting held on, August 29, 2023; Time: 5:00pm – 6:30pm; Location: Varina Library, 1875 New Market Road, Henrico, VA 23231
- Project schedule has been revised to reflect construction starting in 2032 instead of 2028 due to County securing federal funding for right-of-way and construction; newly identified environmental issues and proposed right-of-way acquisition requirements for the proposed design.
- Messer Road Trail Connector Brochure