Mt. Olive Ave and Trolley Lane Improvements​

Project Status: Underway - Design

Estimated Cost: $5.1 million
Start Date: 2026
Estimated End Date: 2027

Magisterial District:   Fairfield  


The County of Henrico will be constructing accommodations to increase pedestrian access and connectivity. The following improvements will be constructed, including: 

  • The removal of the existing connection of Mt. Olive Ave. to Mountain Road and constructing a new connection which reduces the existing skewed orientation. 
  • A right turn lane from Mountain Road to the new connection with Mt. Olive Ave. will be constructed. 
  • Upgrading the existing gravel road which parallels the Dominion Energy transmission line easement. 
  • The removal of the existing connection of Trolley Lane and Mountain Road. 

Estimated Schedule: (Month Year) 

  • Design is underway. 
  • Right-of-way acquisition is underway. 
  • Utility relocation is anticipated to begin in ​the 3rd Quarter, 2025. 
  • Advertisement for construction is anticipated for 2026. 
  • Construction is anticipated to begin 2026.