Nuckols Rd Pedestrian Improvements

Project Status: Underway - Design

Estimated Cost: $1.4 million
Start Date: 2026
Estimated End Date: 2027

Magisterial District:   Brookland  


Design and construct sidewalk on the north side of Nuckols Road between Springfield Rd and Energy Way (formerly Capital One Way). Work will include crosswalks and pedestrian signals at the Nuckols Road and Energy Way intersection.  

Estimated Schedule: (Month Year) 

  • Design is underway.
  • Right-of-way acquisition is anticipated to begin in 2nd Quarter, 2025. 
  • Utility relocation is anticipated to begin in 4th Quarter, 2025. 
  • Advertisement for construction is anticipated in 2026. 
  • Construction is anticipated to begin in 2026.

Contact Us

Sudha Mudgade
(804) 501-4620
[email protected]


Public Works

Henrico Department of Public Works
4305 E. Parham Rd.
Henrico, VA 23228

Phone
(804) 501-4393

[email protected]

Mailing Address
P. O. Box 90775
Henrico, VA 23273-0775

Twitter Facebook

 
Google Translate Icon

Translate