Ridge Road Sidewalk Phase 2

Project Summary

Project Status
Underway - Design
Estimated Cost
$7.6 million
Start Date
2030
Estimated End Date
2032
Magisterial District
Tuckahoe

Project Description

The County of Henrico will be constructing accommodations to increase pedestrian safety, access, and connectivity. The following improvements will be constructed, including:

  • Approximately 1,800-ft of new sidewalk along the north side of Ridge Road from Glendale Drive to N. Parham Road, and approximately 120-ft of new sidewalk along the south side of Ridge Road from Old Providence Circle to Greene Ridge Road.
  • Approximately 690-ft of new shared use path along the north side of Ridge Road from Greene Ridge Road to Glendale Drive.
  • Approximately 20 ADA compliant ramps.
  • A mini-roundabout at the intersection of Ridge Road and Glendale Drive.

Estimated Schedule:

  • Design is underway.
  • Right-of-way acquisition is anticipated to begin in 2027.
  • Utility relocation is anticipated to begin in 2028.
  • Advertisement for construction is anticipated for 2029.
  • Construction is anticipated to begin in 2030.

Progress to Date

A Public Hearing was held on 5/12/2025, at the Tuckahoe Library (TU Meeting Room), 1901 Starling Drive, Henrico, VA 23229, from 5:30pm to 7:00pm.