Ridge Road Sidewalk Phase 2

Project Status: Underway - Design

Estimated Cost: $7.6 million
Start Date: 2030
Estimated End Date: 2032

Magisterial District:   Tuckahoe  


The County of Henrico will be constructing accommodations to increase pedestrian safety, access, and connectivity. The following improvements will be constructed, including:

  • Approximately 1,800-ft of new sidewalk along the north side of Ridge Road from Glendale Drive to N. Parham Road, and approximately 120-ft of new sidewalk along the south side of Ridge Road from Old Providence Circle to Greene Ridge Road.
  • Approximately 690-ft of new shared use path along the north side of Ridge Road from Greene Ridge Road to Glendale Drive.
  • Approximately 20 ADA compliant ramps.
  • A mini-roundabout at the intersection of Ridge Road and Glendale Drive.

Estimated Schedule:

  • Design is underway.
  • Right-of-way acquisition is anticipated to begin in 2027.
  • Utility relocation is anticipated to begin in 2028.
  • Advertisement for construction is anticipated for 2029.
  • Construction is anticipated to begin in 2030.

Progress to Date

A Public Hearing was held on 5/12/2025, at the Tuckahoe Library (TU Meeting Room), 1901 Starling Drive, Henrico, VA 23229, from 5:30pm to 7:00pm.