Fall Line Trail – Spring Park Trailhead
Project Status: Underway - Design
Estimated Cost: TBD
Start Date: 4th Quarter, 2025
Estimated End Date: 2nd Quarter, 2026
Magisterial District: Fairfield
Project Description:
- The County of Henrico will be constructing accommodations to increase pedestrian access and connectivity. The following improvements will be constructed, including:
- Trail restroom facilities on property at the southeast corner of Lakeside Avenue and Park Street and adjacent to the Fall Line Trail.
- Additional trailside amenities
Estimated Schedule:
- Design underway.
- ROW is not anticipated.
- Utility relocation is not anticipated.
- Advertisement for construction is anticipated in the 3rd quarter of 2025.
- Construction is anticipated to begin in the 4th Quarter, 2025.