Staples Mill Road Sidewalk Phase 1
Project Status: Preliminary
Estimated Cost: TBD
Start Date: 2028
Estimated End Date: 2029
Magisterial District: Brookland
Project Description:
The County of Henrico will be constructing accommodations to increase pedestrian access and connectivity. The following improvements will be constructed, including:
- Sidewalk along the northbound Staples Mill Road from the north corner of Courtney Road to the existing sidewalk at the north corner of the Henrico County Public Library Parcel
- Sidewalk along southbound Staples Mill Road connecting the existing sidewalks at the south corner of the Glen Allen High School parcel to the sidewalk along Sharp’s Way
Estimated Schedule
- Design is anticipated to begin 3rd Quarter, 2026.
- Right-of-way acquisition is anticipated to begin in 2027.
- Utility relocation is anticipated to begin in 2028.
- Advertisement for construction is anticipated for 2028.
- Construction is anticipated to begin in 2028.