Thalbro Street Sidewalks

Project Summary

Project Status
Underway - Utility Relocation
Estimated Cost
$900,000
Start Date
4th Quarter, 2026
Estimated End Date
2027
Magisterial District
Brookland

Project Description

The County of Henrico will be constructing accommodations to increase pedestrian access and connectivity. The following improvements will be constructed:  

  • Approximately 900 feet of sidewalk along the northern side of Thalbro Street between Staples Mill Road (Route 33) and Maywill Street.
  • Additional ADA curb ramps and pedestrian crosswalks on the south and west legs at the intersection of  Thalbro Street and Maywill Street. 
  •  

Estimated Schedule: (Month Year) 

  • Design is complete
  • Right-of-way acquisition is complete
  • Utility relocation is anticipated for 4th Quarter, 2026
  • Construction to begin 4th Quarter, 2026