Project Summary
- Project Status
- In Progress
- Estimated Cost
- $16 million
- Start Date
- July 2021
- Magisterial District
- Tuckahoe
Project Description
This project will begin development of the Tuckahoe Park Master Plan adopted by the Henrico Board of Supervisors in 2008 and amended and approved again April 14, 2021- POD2021-00159. The amended master plan by consultants CHA and HG Design incorporated an additional 2.62 acres into the previously approved park master plan. Funding for this project is from Henrico’s voter-approved 2016 Bond Referendum.
On August 25, 2026 the Board of Supervisors awarded a contract to begin the improvements to Tuckahoe Park. The project will add two fully accessible restrooms, one paved parking lot with accessible parking, site lighting, as well as a curb, gutter and storm sewer system. Asphalt multiuse trails, sidewalks and a pedestrian bridge will link the existing athletic fields to a new accessible playground.
Kenbridge Construction Co. is expected to start construction in September 2026, with an anticipated completion date in spring 2028.
Community Amenities:
- Large playground
- Paved trail network
- Additional parking near John Rolfe entrance
- Sports field improvements
- Two new accessible restroom buildings
Schedule:
- Field improvements have begun and will be ongoing.
- The larger construction projects will kick off in September 2026.
- Anticipated completion is set for spring 2028.