Virginia Center Common (VCC) Connector Trail
Project Status: Underway - Design
Estimated Cost: $2.3 million
Start Date: 2nd Quarter, 2026
Estimated End Date: 2026
Magisterial District: Fairfield
The County of Henrico will be constructing pedestrian improvements for approximately 0.4 miles from along Magnolia Ridge Drive from the intersection of Woodman Road Extended to the intersection of Brook Road. Project improvements include, but are not limited to:
- Connect a five-foot-wide sidewalk along the north side of Magnolia Ridge Drive to the intersection of Route 1.
- Construct a 12-foot-wide, two-way bicycle lane with a 3-foot-wide protected buffer adjacent to the sidewalk.
Estimated Schedule
- Design is complete.
- Right-of-way acquisition is underway.
- Utility relocations have been completed.
- Advertisement for construction is anticipated 1st Quarter, 2026.
- Construction is anticipated to begin 2nd Quarter, 2026.