​​Williamsburg Road Pedestrian and Transit Improvements ​

Project Status: Underway

Estimated Cost: ​​$29.2 M​
Start Date: 2029
Estimated End Date: 2030

Magisterial District:   Varina  


The County of Henrico will be constructing accommodations to increase pedestrian access and connectivity. The following improvements will be constructed, including: 

  • Providing continuous pedestrian sidewalks and/or multi-use path along Rt 60 from Charles City Rd to Laburnum Ave. 
  • Pedestrian crossing facilities and lighting at signalized intersections.  
  • Turn lane improvements at Charles City Road, extended turn bays at Laburnum Avenue and an RCUT/directional median at Finlay Street. 

Estimated Schedule: (Month Year) 

  • Design is anticipated to begin 2nd Quarter, 2025 
  • Right-of-way acquisition is anticipated to begin 2026  
  • Utility relocation is anticipated to begin 2027 
  • Advertisement for construction is anticipated to begin 2029 
  • Construction is anticipated to begin 2030 

 

 

 