Site menu

​​Williamsburg Road Pedestrian and Transit Improvements ​

Project Summary

Project Status
Underway - Design
Estimated Cost
​​$26.5 M​
Start Date
2031
Estimated End Date
2032
Magisterial District
Varina

Project Description

The County of Henrico will be constructing accommodations to increase pedestrian access and connectivity. The following improvements will be constructed, including: 

  • Providing continuous pedestrian sidewalks and/or multi-use path along Rt 60 from Charles City Rd to Laburnum Ave. 
  • Pedestrian crossing facilities and lighting at signalized intersections.  
  • Turn lane improvements at Charles City Road, extended turn bays at Laburnum Avenue and an RCUT/directional median at Finlay Street. 

Example of a Restricted Crossing U-Turn (RCUT): Click Here

Estimated Schedule: (Month Year) 

  • Design is underway.
  • Right-of-way acquisition is anticipated to begin 2028. 
  • Utility relocation is anticipated to begin 2029.
  • Advertisement for construction is anticipated to begin 2030.
  • Construction is anticipated to begin 2031.