Williamsburg Road Pedestrian and Transit Improvements
Project Summary
- Project Status
- Underway - Design
- Estimated Cost
- $26.5 M
- Start Date
- 2031
- Estimated End Date
- 2032
- Magisterial District
- Varina
Project Description
The County of Henrico will be constructing accommodations to increase pedestrian access and connectivity. The following improvements will be constructed, including:
- Providing continuous pedestrian sidewalks and/or multi-use path along Rt 60 from Charles City Rd to Laburnum Ave.
- Pedestrian crossing facilities and lighting at signalized intersections.
- Turn lane improvements at Charles City Road, extended turn bays at Laburnum Avenue and an RCUT/directional median at Finlay Street.
Example of a Restricted Crossing U-Turn (RCUT): Click Here
Estimated Schedule: (Month Year)
- Design is underway.
- Right-of-way acquisition is anticipated to begin 2028.
- Utility relocation is anticipated to begin 2029.
- Advertisement for construction is anticipated to begin 2030.
- Construction is anticipated to begin 2031.