Project Status: Underway - Utility Relocation
Estimated Cost: $7.4 million
Start Date: 1st Quarter, 2025
Estimated End Date: 2027
Magisterial District: Brookland
The County of Henrico will be constructing road improvements on Bethlehem Road between Libbie Avenue and Staples Mill Road. The following improvements will be constructed, including:
- A 3-lane road section.
- Pedestrian improvements include a shared-use path, sidewalk, crosswalks, and ADA ramps.
- A roundabout at the intersection of Libbie Avenue and Bethlehem Road.
Estimated Schedule:
- Design began in January 2019.
- Right-of-way acquisition is complete.
- Utility relocations are underway.
- Advertisement for construction is complete.
- Construction is anticipated to begin in the 1st quarter of 2025.
- Project completion is anticipated in 2027.
Progress to Date
- A citizen information meeting was held at the Libbie Mill Library, 2100 Libbie Lake E. Street, Henrico, Virginia 23230, on Wednesday, July 29, 2020 from 5:30-6:30 p.m.