County-Wide Pedestrian Signal Improvements

Project Status: Underway - Design

Estimated Cost: $1.2 million
Start Date: 2nd Quarter, 2025
Estimated End Date: 2nd Quarter, 2025

Magisterial District:   Three Chopt   Tuckahoe  


The County of Henrico will be constructing accommodations to increase pedestrian access and connectivity. The following improvements will be constructed, including: 

  • Pedestrian Hybrid Beacons (PHB) at different locations throughout the County, including, but not limited to, intersections at Pump Road and Old Prescott Road, Pump Road and Carisbrook Drive, and Twin Hickory Road and Hickory Bend Road. 
  • How it works: https://www.youtube.com/embed/eKQOjt3p5JA  

Estimated Schedules:

Pump Road and Old Prescott Road                             

  • Design began 2023.
  • Right-of-way acquisition began Jun- 2024. 
  • Utility relocation is anticipated 3rd Quarter, 2024. 
  • Advertisement for construction is not anticipated. 
  • Construction is anticipated 2nd Quarter, 2025.

Twin Hickory Road and Hickory Bend Drive                            

  • Design began Jan- 2023.
  • Right-of-way acquisition began August- 2024.
  • Utility relocation is anticipated 3rd Quarter, 2024.
  • Advertisement for construction is not anticipated.
  • Construction is anticipated 2nd Quarter, 2025.

Pump Road and Carisbrook Drive                                               

  • Design is anticipated to begin August- 2024 
  • Right of way acquisition is anticipated 3rd Quarter, 2025. 
  • Utility relation is anticipated 3rd Quarter, 2025. 
  • Advertisement for construction is not anticipated. 
  • Construction is anticipated 1st quarter, 2026. 

 

Contact Us

Ryan Levering
(804) 501-4244
[email protected]


Public Works

Henrico Department of Public Works
4305 E. Parham Rd.
Henrico, VA 23228

Phone
(804) 501-4393

[email protected]

Mailing Address
P. O. Box 90775
Henrico, VA 23273-0775

Twitter Facebook

 
Google Translate Icon

Translate