Creighton Road Sidewalk
Project Status: Underway
Estimated Cost: $500,000
Start Date: June 2022
Estimated End Date: September 2022
Magisterial District: Fairfield
This project involves the design and construction of approximately 1,100 feet of a new 5-foot wide sidewalk along the south side of Creighton Road between Harvest Crest Drive and Carolee Drive. The proposed sidewalk is to be constructed within existing right of way and maintain a 2-foot wide grass utility strip to match the existing sidewalk typical section along Creighton Road.
-
Estimated Schedule: (Month Year)
- Design is complete.
- Right-of-way acquisition is complete.
- Utility relocation is complete.
- Advertisement is complete.
- Construction is anticipated June 2022.
- Project completion is anticipated September 2022.