Site menu

Creighton Road Sidewalk

Henrico County Archives

This page content is archived for historical purposes.

Project Summary

Project Status
Completed
Estimated Cost
$500,000
Start Date
June 2022
Estimated End Date
September 2022
Magisterial District
Fairfield

Project Description

This project involves the design and construction of approximately 1,100 feet of a new 5-foot wide sidewalk along the south side of Creighton Road between Harvest Crest Drive and Carolee Drive. The proposed sidewalk is to be constructed within existing right of way and maintain a 2-foot wide grass utility strip to match the existing sidewalk typical section along Creighton Road.

Map of project area. An orange line between Leslie Ann Drive and Carolee Drive denotes new sidewalk construction. A green line going off the edge of the map beginning at Laburnum Avenue denotes other upcoming sidewalk projects. Purple lines, scattered around Creighton Road and Laburnum Avenue denote existing sidewalks.

Estimated Schedule

  • Design is complete.
  • Right-of-way acquisition is complete.
  • Utility relocation is complete.
  • Advertisement is complete.
  • Construction is anticipated June 2022.
  • Project completion is anticipated September 2022.