Dellrose Avenue Drainage System Improvements

Project Status: Underway - Design

Estimated Cost: $5 million
Start Date: December 2021
Estimated End Date: June 2022

Magisterial District:   Brookland  


The County of Henrico will be constructing stormwater drainage improvements to replace eroded stormwater infrastructureThe following improvements will be constructed, including: 

  • New concrete stormwater pipes to replace failing metal pipes located running east from the corner of Cedar Croft Street and Dellrose Avenue. 
  • Sanitary Sewer Improvements for existing connections running adjacent to the proposed stormwater improvements. 

Estimated Schedule: (Month Year) 

  • Design is underway. 
  • Right-of-way acquisition is not anticipated.  
  • Utility relocation is not anticipated. 
  • Advertisement for construction is anticipated September 2021. 
  • Construction anticipated December 2021. 
  • Project completion anticipated June 2022
 