Dellrose Avenue Drainage System Improvements
This page content is archived for historical purposes.
Project Summary
- Project Status
- Underway - Design
- Estimated Cost
- $5 million
- Start Date
- December 2021
- Estimated End Date
- June 2022
- Magisterial District
- Brookland
Project Description
The County of Henrico will be constructing stormwater drainage improvements to replace eroded stormwater infrastructure. The following improvements will be constructed, including:
- New concrete stormwater pipes to replace failing metal pipes located running east from the corner of Cedar Croft Street and Dellrose Avenue.
- Sanitary Sewer Improvements for existing connections running adjacent to the proposed stormwater improvements.
Estimated Schedule: (Month Year)
- Design is underway.
- Right-of-way acquisition is not anticipated.
- Utility relocation is not anticipated.
- Advertisement for construction is anticipated September 2021.
- Construction anticipated December 2021.
- Project completion anticipated June 2022