Lakeside Avenue Bridge Replacement
Project Status: Underway - Utility Relocation
Estimated Cost: $9 million
Start Date: 2nd Quarter, 2026
Estimated End Date: 2027
Magisterial District: Fairfield
The County of Henrico will be removing the existing Lakeside Avenue bridge crossing over North Run Creek, located between Fairway Avenue and Club Road, and constructing a new bridge in the same location. The following improvements will be constructed, including:
- Necessary storm sewer and waterline improvements.
- Removal of the existing bridge.
- Construct a new bridge on existing alignment.
- Improvements to both bridge approach roadways, including Guardrail System improvements.
Estimated Schedule:
- Design is complete.
- Right-of-way acquisition complete.
- Utility relocation is underway.
- Advertisement for construction is anticipated in 1st Quarter, 2026.
- Construction is anticipated to begin in 2nd Quarter, 2026.
- Project completion is anticipated in 2027.