Libbie Avenue Road Diet
Project Status: Underway - Design
Estimated Cost: $3.8 million
Start Date: 2nd Quarter, 2026
Estimated End Date: 2027
Magisterial District: Brookland
The County of Henrico will construct a combination of shared-use path and two-way bike lanes along the east side of Libbie Avenue between West Broad Street and Bethlehem Road. On-street parking will be maintained between Libbie Mill West Boulevard/N. Crestwood Avenue and Lehigh Circle. Lane reconfiguration will include removing the slip lane from northbound Libbie Avenue onto Libbie Mill West Boulevard and making the current right through lane a right-turn only lane. Additionally, the dedicated right-turn lane between Libbie Mill West Boulevard and Indigo Road will be removed in the northbound direction and one through lane will be removed in the southbound direction between these two intersections. A two-way center turn lane will be provided between Indigo Road and Bethlehem Road.
Estimated Schedule
- Design currently underway.
- Right of Way is complete.
- Utility relocations are complete.
- Advertisement is anticipated in 1st Quarter, 2026.
- Construction is anticipated to begin 2nd Quarter, 2026.
- Project completion is anticipated: 2027.
Progress to Date
- On Monday, October 7, 2024, the Henrico County Department of Public Works held a public information meeting from 5:30pm to 7:00pm at the Libbie Mill Library. Materials from the meeting can be found in the Documents section below.