North Gayton Road Sidewalk Project

Henrico County Archives

This page content is archived for historical purposes.

Project Summary

Project Status
Completed
Estimated Cost
$1.24 Million total
Start Date
September 2019
Estimated End Date
January 2020
Magisterial District
Three Chopt

Project Description

The County of Henrico will be constructing sidewalk along the west side of North Gayton Road, between Graham Meadows Drive and Causeway Drive

Estimated Schedule

  • Design is underway
  • Right-of-way acquisition is complete
  • Utility relocation is complete
  • Construction for this project is completed 

Progress to Date

  • A Citizen Information Meeting was held at Gayton Elementary School on Tuesday, March 20, 2018 from 6 PM – 7 PM.  The brochure provided at the meeting is now available.