Project Summary

Project Status
Completed
Estimated Cost
998,000
Start Date
2nd Quarter, 2024
Estimated End Date
3rd Quarter, 2024
Magisterial District
Brookland

Project Description

The County of Henrico will be constructing approximately 620 linear feet of 5-foot wide sidewalk, 430 linear feet of new curb & gutter and storm sewer along the 0.45-mile project corridor between Shrader Road and Hungary Spring Road. The following improvements will be constructed, including:

  • Curb & gutter
  • Curb cuts
  • Drainage improvements
  • New ADA ramps
  • 2 GRTC bus pads

Estimated Schedule:

  • Design is underway.
  • Right-of-way acquisition is complete.
  • Advertisement for construction is complete. 
  • Construction started 2nd Quarter, 2024.
  • Project completion is anticipated 3rd Quarter, 2024. 

Progress to Date

  • Pre-construction meeting held April 11, 2024
  • Construction start date April 29, 2024