Ridge Road Sidewalk Phase 2

Project Status: Underway - Design

Estimated Cost: $6 million
Start Date: 2027
Estimated End Date: 2028

Magisterial District:   Tuckahoe  


The County of Henrico will be constructing accommodations to increase pedestrian access and connectivity. The following improvements will be constructed, including:

  • Approximately 1,800-ft of new sidewalk along the north side of Ridge Road from Glendale Drive to N. Parham Road, and approximately 120-ft of new sidewalk along the south side of Ridge Road from Old Providence Circle to Greene Ridge Road.
  • Approximately 690-ft of new shared use path along the north side of Ridge Road from Greene Ridge Road to Glendale Drive.
  • Approximately 20 ADA compliant ramps.

Estimated Schedule: (Month Year)

  • Design is underway
  • Right-of-way acquisition is anticipated to begin 2nd Quarter 2026
  • Utility relocation is anticipated to begin 3rd Quarter, 2027
  • Advertisement for construction is anticipated to begin 4th Quarter, 2026
  • Construction is anticipated to begin 2027

Progress to Date

A Public Hearing was held on 5/12/2025, at the Tuckahoe Library (TU Meeting Room), 1901 Starling Drive, Henrico, VA 23229, from 5:30pm to 7:00pm.