Ridgefield Parkway Sidewalk, Phase II

Project Status: Completed

Estimated Cost: $500,000
Start Date: April 2021
Estimated End Date: May 2021

Magisterial District:   Tuckahoe  


The County of Henrico will be constructing accommodations for pedestrian access and connectivity. The following improvements will be constructed, including: 

  • Approximately 800 linear feet of sidewalk on the south side of Ridgefield Parkway beginning at Glen Eagles Drive and connecting to the existing sidewalk to the west. 

Estimated Schedule:

  • Design is completed 
  • Right-of-way acquisition is completed
  • Utility relocation is completed
  • Advertisement for construction is completed 
  • Construction is completed