Ridgefield Parkway Sidewalk, Phase I
This page content is archived for historical purposes.
Project Summary
- Project Status
- Completed
- Estimated Cost
- $1.3 million total
- Start Date
- July 2021
- Estimated End Date
- December 2021
- Magisterial District
- Three Chopt Tuckahoe
Project Description
Henrico County is constructing approximately 1.0 mile of sidewalk on Ridgefield Parkway between Pump Road and Falconbridge Drive. The design will evaluate placement of a 4’ wide sidewalk with a 2’ utility strip, or another acceptable alternative. Crosswalk and pedestrian signals will be designed and installed as part of the project.
Estimated Schedule
- Design is complete
- Right-of-way acquisition is complete
- Utility relocation is not anticipated
- Advertisement for construction is complete
- Construction is anticipated to begin July 2021
- Project completed December 2021
Progress to Date
- A Citizen Information Meeting for this project was held on January 19, 2016.